PMI-SP - Developing the Work Breakdown Structure (WBS) - Work Breakdown Structure and Risk Management
Expert
1/5
When applying rolling wave planning in a project with high-risk WBS components, what is the most appropriate approach for risk-adjusted scheduling?
a.
Create detailed schedules for near-term WBS packages while maintaining summary-level estimates for future work
b.
Focus scheduling efforts on high-risk WBS components while applying standard duration estimates to low-risk activities
c.
Develop comprehensive detailed schedules for all WBS components at the start to ensure complete risk coverage and mitigation plans
d.
Schedule all WBS components with equal detail regardless of time horizon to maintain consistency in risk assessment