PMI-SP - Documenting Lessons Learned - Utilizing Lessons Learned to Improve Future Project Scheduling
Expert
1/12
Which method is most effective for ensuring lessons learned from past scheduling issues become embedded in organizational scheduling practices?
a.
Developing extensive documentation of all schedule variances and storing them in a centralized database for future reference
b.
Conducting monthly meetings to review historical schedule performance data and update current scheduling guidelines
c.
Creating standardized scheduling templates that incorporate proven adjustments from past projects
d.
Implementing mandatory training sessions that focus on reviewing past scheduling mistakes and their resolutions