Register
4:59
Stop
PMI-SP - Earned Value Management (EVM) - Cost Performance Index (CPI)
Intermediate
1/5
In a complex IT project, you need to decide the optimal depth for your Resource Breakdown Structure (RBS). What is the recommended number of hierarchical levels to ensure effective resource management?
a.
10-12 levels capturing every minute detail of resource categorization
b.
2 levels focusing on broad categories and specific resources only
c.
3-5 levels based on project complexity and size
d.
At least 7-8 levels to ensure maximum detail and granularity in resource allocation
Intermediate