PMI-SP - Earned Value Management (EVM) - Schedule Variance (SV)
Expert
1/33
If a project's Schedule Variance (SV) alternates between +$8,000 and -$8,000 over six weekly measurements, which sampling frequency would provide the most meaningful analysis?
a.
Monthly measurements to minimize the impact of short-term schedule fluctuations
b.
Weekly measurements to maintain consistent data points for variance tracking
c.
Bi-weekly measurements to capture the full variation cycle
d.
Daily measurements to establish detailed trend patterns across multiple project phases and activities