PMI-SP - Estimating Activity Durations - Analogous Estimating
Expert
1/59
In a data center migration project, your team leaders have submitted detailed estimates for server relocation, network configuration, and system testing. Which factor would most significantly impact the accuracy of bottom-up estimating in this context?
Expert