PMI-SP - Estimating Activity Durations - Analogous Estimating
Expert
1/59
In a data center migration project, your team leaders have submitted detailed estimates for server relocation, network configuration, and system testing. Which factor would most significantly impact the accuracy of bottom-up estimating in this context?
a.
The comprehensive analysis of historical data from previous migrations and their correlation to current estimates
b.
The sequential arrangement of tasks based on technical prerequisites and operational constraints
c.
The interdependencies between work packages and their effect on resource allocation
d.
The detailed scheduling of parallel activities and their impact on the overall project timeline and resources