PMI-SP - Estimating Activity Durations - Analogous Estimating
Expert
1/5
In which phase of project lifecycle does Analogous Estimating provide the most value?
a.
Early planning phase when detailed information is still uncertain
b.
Throughout all project phases as it provides consistent baseline comparisons
c.
Mid-project phase when most requirements have been fully documented
d.
During the execution phase when actual costs and variances become more apparent
Expert