When reviewing a project's Schedule Variance (SV) of -$50,000 alongside actuals that show completed tasks, what is the most accurate explanation of the project's status?
a.
The project is behind schedule and has delivered less value than planned
b.
The scheduling performance indicates excess resource allocation with positive outcomes
c.
The project has exceeded its baseline time estimates but remains financially stable
d.
The project is progressing faster than planned but has negative cost implications