In schedule risk management, when identifying contingency reserves, which factor is most crucial for determining the size of time buffers?
a.
Historical data from similar projects and their variance patterns
b.
The total number of activities in the critical path multiplied by a standard factor of 15%
c.
The complexity rating of project deliverables combined with stakeholder tolerance thresholds
d.
A fixed percentage based on the project's overall duration and organizational standards