PMI-SP - Progress Measurement and Reporting - Milestone Trend Analysis (MTA)
Intermediate
1/5
During activity duration estimation for a major event management project, your team has access to three estimates for each activity: an optimistic estimate of 2 days, a most likely estimate of 4 days, and a pessimistic estimate of 12 days. Which value represents the expected duration using PERT?