PMI-SP - Reporting Schedule Status to Stakeholders - Critical Path Analysis in Schedule Reporting
Expert
1/5
When reviewing a critical path analysis report, what key pattern best indicates schedule acceleration is needed?
a.
Multiple non-critical activities displaying extended duration patterns over time
b.
Three consecutive periods of negative float on critical activities
c.
Repeated instances of resource overallocation causing baseline deviations in critical tasks
d.
Five or more activities showing positive float trends across multiple reporting cycles