When a schedule risk matrix reveals multiple high-impact threats, what is the most effective sequence for communicating findings to project stakeholders?
a.
Schedule individual meetings with each stakeholder group to discuss their specific concerns and gather feedback on proposed solutions
b.
Develop a color-coded dashboard showing all identified risks and send weekly automated updates to the entire stakeholder database
c.
Create a comprehensive risk breakdown structure and distribute detailed technical analyses to all organizational levels for thorough review
d.
Present the top three risks with specific impact values, followed by mitigation options and their associated costs
Expert