PMI-SP - Reporting Schedule Status to Stakeholders - Use of Visual Tools and Dashboards in Schedule Reporting
Intermediate
1/5
During cost variance analysis, your team has developed multiple EAC scenarios based on different earned value metrics. How frequently should these EACs be recalculated for optimal decision-making?
Intermediate