In Monte Carlo schedule analysis, which key indicator best identifies the presence of competing critical paths in the network?
a.
Increasing standard deviation of activity durations across all project paths
b.
Multiple peaks in the completion date distribution histogram
c.
Sequential correlation patterns in the total float distribution analysis
d.
Consistent variances between early and late finish dates for all activities