PMI-SP - Schedule Risk Analysis and Mitigation - Monte Carlo Simulation in Schedule Risk Analysis
Intermediate
1/5
During cost variance analysis, your team has developed multiple EAC scenarios based on different earned value metrics. How frequently should these EACs be recalculated for optimal decision-making?