PMI-SP - Scheduling Principles and Concepts - Critical Path Method (CPM)
Expert
1/5
In Critical Path Method (CPM), when analyzing a network diagram with multiple paths sharing similar durations but different resource requirements, what determines the selection of tasks to compress first?
a.
The individual task duration variances combined with their respective resource loading patterns
b.
The sequence of activities with the highest number of dependent tasks in parallel paths
c.
The ratio of crash cost to duration reduction for each task on competing paths
d.
The available resource capacity and the total number of predecessors for each task on related paths
Expert