During resource optimization, what is the primary benefit of implementing Fast-Tracking in conjunction with resource calendars?
a.
It enables parallel execution of activities while ensuring resource availability matches peak demand periods
b.
It maximizes resource utilization by extending the project duration and distributing work across multiple calendar cycles
c.
It reduces resource conflicts by sequentially allocating resources based on their standard availability patterns
d.
It optimizes resource allocation through systematic compression of non-critical activities during peak resource demand
Expert