PMI-SP - Scheduling Principles and Concepts - Work Breakdown Structure (WBS)
Expert
1/62
In assembling a Work Breakdown Structure (WBS) for an international conference, several stakeholders have different expectations about the format and structure. What is the most effective method for standardizing the WBS format?
a.
Create separate WBS branches for each stakeholder's requirements and merge them later based on priority
b.
Implement a comprehensive numbering scheme that incorporates both geographical and functional aspects of each component
c.
Establish parallel hierarchies for different stakeholder groups and link them through integration points
d.
Apply a uniform coding system for all deliverables and work packages