PMI-SP - Scheduling Principles and Concepts - Work Breakdown Structure (WBS)
Expert
1/5
When dealing with multiple vendors in a construction project's WBS, what is the most effective way to structure vendor-related work packages?
a.
Establish independent vendor tracking systems parallel to the main WBS to maintain clear separation of responsibilities
b.
Combine all vendor activities into a single work package to streamline coordination and management processes
c.
Create separate control accounts for each vendor and link them to the relevant deliverables
d.
Create detailed vendor management packages that include every possible interaction and communication pathway with suppliers
Expert