PMP - Business Management - Strategic Alignment
Intermediate
1/29
In Resource Estimation, the ________ technique involves using historical data from similar projects to estimate resource requirements for the current project.
a.
Analogous estimating
b.
Three-point estimating
c.
Parametric estimating
d.
Bottom-up estimating