PMP - Procurement Planning - Bid Documents
Intermediate
1/5
During the procurement phase of a large-scale renewable energy project, you are tasked with evaluating the bid documents submitted by various suppliers. One of the bid documents presents an innovative wind turbine design that promises significantly higher efficiency rates than standard models. However, upon closer inspection, you realize the supplier has not provided any verifiable performance data or endorsements from industry experts to substantiate their claims. Considering the potential impact of this technology on project success and sustainability goals, but also the risk associated with unproven innovations, what is your next step?