PMP - Resource Allocation - Resource Calendar
Intermediate
1/17
During the execution phase of your project, while conducting regular risk monitoring, you discover that a high-impact risk previously identified is now significantly less likely to occur due to recent regulatory changes in the industry. This risk had considerable resources allocated for its mitigation. Given this new information, what is the best course of action?