You are managing a project that involves multiple stakeholders with varying expectations. During execution, one of the stakeholders requests an unplanned addition to the project scope. Which Performance Measurement Baseline (PMB) will this likely impact?
a.
Quality Baseline
b.
Scope Baseline
c.
Schedule Baseline
d.
Cost Baseline