PMP - Scope Verification and Control - Requirements Management
Intermediate
1/5
A project manager is overseeing a project involving a new technology that the team is unfamiliar with. Stakeholders are concerned about the tight schedule and budget. According to the PMBOK Guide Seventh Edition, what is the most appropriate action for the project manager to take to address the team's training needs under these constraints?
a.
Instruct the team to self-study the new technology during non-working hours, maintaining the original project timelines.
b.
Integrate the necessary training into the project plan and discuss potential schedule and budget impacts with stakeholders.
c.
Replace current team members with external experts who have experience with the technology to keep the project on schedule.
d.
Proceed with the project using the team's existing skills, focusing on tasks that do not require the new technology.
Intermediate