PMP - Scope Verification and Control - Requirements Management
Intermediate
1/5
A project manager is overseeing a project involving a new technology that the team is unfamiliar with. Stakeholders are concerned about the tight schedule and budget. According to the PMBOK Guide Seventh Edition, what is the most appropriate action for the project manager to take to address the team's training needs under these constraints?