PMP - Stakeholders - PMBOK 7th edition - Stakeholder Engagement Plan
Intermediate
1/5
In the context of the PMBOK Guide Seventh Edition, which statement accurately reflects the role of the Stakeholder Engagement Plan during project execution?
a.
It ensures that stakeholders are managed solely through formal channels and documented communications.
b.
It guides how to interact with stakeholders based on their needs, expectations, interests, and potential impact on the project.
c.
It specifies that project team members are responsible for their own stakeholder engagement activities.
d.
It catalogues all stakeholders with no need for further analysis or updates throughout the project.