PRINCE2 Practitioner - Applying PRINCE2 Practices - Change
Intermediate
1/5
In PRINCE2, when should quality methods be reviewed as part of the quality management process?
a.
When executive stakeholders specifically request an evaluation of quality processes
b.
During the initial setup of the project and at project closure according to the baseline plan
c.
At stage boundaries and when significant changes occur to the project environment
d.
Only after quality metrics have been established by the quality assurance team
Intermediate