Agile Project Management
Beginner
1/20
As the project deadline approaches, your Agile team realizes that some innovative features may not be completed in time. What course of action does the team take to ensure a successful delivery?
a.
Work overtime hours to ensure all innovative features are completed for the deadline
b.
Push back the deadline and risk disappointing stakeholders in order to maintain all innovative aspects
c.
Prioritize the most valuable and achievable features, creating a Minimal Viable Product for release
d.
Eliminate all innovative features and deliver a basic version of the product
e.
Rush through the remaining work, sacrificing quality for speed
f.
Delegate responsibility for completion of innovative features to an external team
Beginner