A Scrum team you manage has recently onboarded two junior developers. While they are quick learners and enthusiastic, they do need support and mentoring from senior team members. How should you adjust capacity planning given this situation?
a.
Exclude the new developers from the team's velocity calculation
b.
Assume the new developers to be as productive as others and plan sprints accordingly
c.
Allocate time for mentoring in the team's planned capacity and take into account the learning curve of new developers
d.
Provide extra training to new developers outside of work hours