In a Bow-Tie Analysis diagram, what does the center knot represent?
a.
The risk event or hazard being analyzed
b.
The intersection point where causes and consequences meet in the risk analysis process
c.
The primary control measures implemented for risk prevention and mitigation strategies
d.
The combined set of preventive and reactive barriers established for the project