In project management, which statement best describes a violation of the 100% Rule when decomposing work packages?
a.
Each work package has been assigned unique identifiers and clear completion criteria
b.
The sum of child level activities equals 95% of the parent work package
c.
The child level activities have been subdivided into smaller tasks meeting all project deliverables
d.
The project milestones and dependencies have been integrated into all work package levels