A project manager is using parametric estimating to calculate the total cost of manufacturing custom parts. The cost per part is $75, and the project requires 150 parts. Additionally, there is a fixed tooling cost of $2,500. What is the total estimated cost for the project?
a.
$15,000
b.
$14,250
c.
$13,750
d.
$12,500