In PRINCE2, what is the Project Manager's key responsibility when receiving new risks identified during the Controlling a Stage process?
a.
Generate a new Work Package for each risk identified and assign them to Team Managers with appropriate risk response measures
b.
Escalate all potential risks to the Project Board regardless of severity while continuing normal stage activities as scheduled in the baseline plan
c.
Create an Exception Report for all risks that exceed the risk tolerance defined in the Stage Plan and wait for Project Board approval
d.
Update the Risk Register and analyze each risk using the chosen risk management approach