Agile Project Management - Agile Manifesto
Expert
1/31
The development team has completed a sprint but hasn't shown it to the client yet. What should be the next step based on Agile principles?
a.
Hold a team retrospective without the client.
b.
Initiate the next sprint.
c.
Document the completed work and share it with the stakeholders.
d.
Ask the client to visit the development site.
e.
Send the completed work to the client via email.
f.
Demonstrate the completed work to the client.