Despite your team delivering the sprint goals, the stakeholders are unhappy with the output. They say it doesn't meet their requirements which were not part of your Definition of Done. What could be the Scrum Master's appropriate response?
a.
Instruct the team to work additionally to meet the stakeholder's requirements
b.
Ask the product owner to manage stakeholder expectations
c.
Ignore the stakeholders as the team is delivering according to the Definition of Done
d.
Facilitate a meeting with team and stakeholders to understand their requirements and revise the Definition of Done as necessary.