Stakeholders ask for a guaranteed delivery date based on the backlog. Which response is most appropriate
a.
Provide a forecasted completion date range based on past velocity and capability
b.
Commit to the date the stakeholder has proposed
c.
Refuse to give any date until all the work is completed
d.
Ask the development team to add more hours to their work days to meet the proposed date