PMI-PBA - Agile Methodologies in Business Analysis
Expert
1/5
During Sprint Planning, what is the recommended maximum duration for a Sprint Planning session in a one-month sprint?
a.
10 hours with scheduled breaks for team collaboration
b.
12 hours split between backlog refinement and task creation
c.
16 hours distributed across multiple days to allow team reflection and adjustments
d.
8 hours
Expert