In Decision Tree Analysis for risk management, what characteristic must branch probability values exhibit to maintain mathematical accuracy?
a.
Branch probabilities should always decrease as decision paths extend further from root nodes
b.
All branch probabilities must reflect the highest probability outcomes in the risk register
c.
All probabilities at each chance node must sum to exactly 1.0
d.
The sum of all terminal node probabilities must equal the initial project risk score