PMI-RMP - Ethics in Risk Management
Intermediate
1/5
What is the primary reason for tracking workarounds in project risk management?
a.
To evaluate team performance in handling unexpected project challenges and events
b.
To maintain detailed records of all project changes made by the stakeholders throughout the project lifecycle
c.
To identify recurring patterns and improve future risk planning
d.
To ensure compliance with organizational standard operating procedures for risk responses