PMI-RMP - Risk Appetite and Tolerance
Intermediate
1/5
Which aspect of a checklist is most crucial when implementing it across multiple project phases in risk assessment?
a.
Customized risk response templates aligned with organizational process assets
b.
Sequential arrangement of risks based on their probability and impact matrices
c.
Standardized categorization of risk types
d.
Comprehensive listing of all historical project risks and their detailed mitigation strategies