PMI-SP - Activity Definition and Sequencing
Expert
1/5
During schedule compression planning, what is the most accurate method to determine the break-even point between fast tracking and crashing costs?
a.
Evaluate the cumulative impact of resource allocation changes on both schedule and budget baselines
b.
Compare the resource utilization rates and overtime expenses across all project phases and activities
c.
Calculate the total cost variance per duration unit saved for each technique
d.
Analyze the cost-benefit ratio of implementing multiple compression techniques simultaneously
Expert