PMI-SP - Critical Path Method (CPM)
Expert
1/5
In CPM schedule risk analysis, what represents the optimal threshold for determining activity duration contingency based on probabilistic calculations?
a.
The mean value of all activity durations plus two standard deviations from historical data
b.
The 85th percentile of simulated activity durations across critical paths
c.
The statistical variance between planned and actual durations multiplied by complexity factors
d.
The combined sum of expected durations and risk factors for all parallel network paths