PMI-SP - Finalizing the Schedule
Expert
1/100
Which specific metric best demonstrates the effectiveness of Schedule Quality Assurance activities in a project?
a.
The percentage of activities with properly allocated resources and detailed work breakdown structures
b.
The reduction in schedule variance trends over sequential reporting periods
c.
The frequency of schedule updates multiplied by the number of approved change requests
d.
The number of completed milestone reviews and schedule baseline updates during the project lifecycle