PMI-SP - Schedule Compression Techniques
Intermediate
1/5
In a complex project, when should Actual Cost (AC) values be updated for the most accurate project performance analysis?
a.
When the project manager completes the cost validation process
b.
When all project stakeholders submit their final cost approvals for review
c.
At predetermined intervals based on management's reporting preferences
d.
As costs are incurred and recorded in the accounting system
Intermediate