During schedule network analysis, a float variance analysis reveals that the current schedule has a total float of -10 days on a secondary path. What should the project manager conclude?
a.
The project schedule has multiple competing critical paths that need to be optimized
b.
The secondary path requires extensive resource leveling to align with the critical path duration
c.
The schedule compression techniques must be applied to reduce the overall project duration
d.
The project has an unrealistic schedule that needs immediate revision