A project manager notices some requirements in the Requirements Traceability Matrix (RTM) are obsolete. What timing pattern best demonstrates strong requirement lifecycle management?
a.
Weekly RTM reviews with requirement owners to assess and update requirement statuses
b.
Bi-weekly updates to RTM entries following scheduled team meetings and project milestone completions
c.
Quarterly assessments of RTM entries combined with extensive stakeholder reviews for comprehensive updates
d.
Monthly reviews of RTM updates based on team feedback and change request documentation to ensure alignment
Intermediate