Register
100:00
Stop
PMP - Earned Value Management
Master
1/100
As a project manager, you are monitoring a project's progress and gather the following data: Earned value (EV) is $75,000, actual cost (AC) is $80,000, planned value (PV) is $70,000, and the Budget at Completion (BAC) is $100,000. If management provided an additional $20,000 as a reserve but you still want to meet the original budget of $100,000, what would be the new To-Complete Performance Index (TCPI)?
a.
0.89
b.
1.25
c.
1.13
d.
0.94
Master