During iteration planning, the Project Manager realizes that a task has been underestimated. What should the team do?
a.
Delegate the underestimated task to an additional team member
b.
Split the task into smaller tasks without re-estimating
c.
Increase the length of the iteration
d.
Remove the underestimated task from the current iteration
e.
Re-estimate the task and adjust the iteration plan
f.
Ignore the discrepancy and follow the original plan