Ideal Days
Ideal Days is a time-based estimation unit used in Agile to measure the effort needed to complete a task or user story by assuming that the team member faces no distractions or obstacles. This unit provides an estimation of how long it would take in terms of perfect working days to finish the job. β¦
Agile Project Management - Ideal Days Example Questions
Test your knowledge of Ideal Days
Question 1
In a project, a team member estimates 2 ideal days to complete a specific task. However, she can only work 50% of her time on this task. How long will it take her to complete the task?
Question 2
Your Agile team consists of 5 members, and together they usually complete 10 ideal days of work in one calendar day. However, the majority of the team (4 members) is attending a workshop for the next two days. The remaining team member, who is not attending the workshop, was left to complete a task estimated at 4 ideal days. Assuming that each team member contributes equally to the team's productivity, what is the expected completion date for the task?
Question 3
You have estimated a task will take 4 ideal days but due to an unforeseen issue, it might take twice the estimated time. How should you adjust the task estimation?