Burn-down Chart

5 minutes 5 Questions

A burn-down chart is a visual representation of the remaining work to be completed in a project against the time left to complete it. It is an essential tool in Agile project management to assess sprint progress and team performance. The chart is updated daily, allowing the team to identify any issues that may impact the project schedule and make adjustments accordingly. By providing a clear picture of the project's progress, the burn-down chart helps foster collaboration, transparency, and continuous improvement within the team.

Guide to Burn-down Chart in Agile Project Management

What is Burn-down Chart?
The Burn-down chart is a graphical depiction of work left to do versus time in Agile project management. It is a widely used method for tracking the progress of work in agile projects and can visually represent what amount of work remains over a given timeframe and its completion rate.

Why is it Important?
Burn-down Chart provides transparency and predicts when all of the work will be completed. It visualizes the amount of work done and the work left to do thereby assisting the project team to optimally manage their work and respond to changes.

How it works?
Burn-down charts are updated daily and reflect the total effort remaining relative to the end of the sprint. It starts with the total amount of effort identified for the sprint and each day the amount of work completed is subtracted from this total to give the remaining effort.

Exam Tips: Answering Questions on Burn-down Chart
1. Understand the Concept: Make sure to thoroughly understand the purpose and functioning of Burn-down charts. Be able to explain them and their benefits.
2. Interpretation Skills: Know how to read and interpret the information from the chart. This is essential as the exam will test this.
3. Real-life examples: Relate with real-world examples for a better understanding and response in an exam.
4. Practice Problems: Solve practice problems based on Burn-down charts to strengthen your preparation.
5. Agile Project Management Specific: Understand how the Burn-down chart fits into Agile project management and why it is preferred.

Test mode:
Agile Project Management - Agile Metrics Example Questions

Test your knowledge of Amazon Simple Storage Service (S3)

Question 1

In a burn-down chart, you observe the actual work remaining line rising above the ideal burn-down line, then plateauing horizontally while the sprint continues. What does this pattern most likely indicate?

Question 2

Your team's burn-down chart is showing more substantial progress in the first few days of the sprint, then it plateaus. What could be causing this?

Question 3

In the burn-down chart, the team's progress isn't consistent. There's a sudden drop halfway through. As a Scrum Master, what might be the best explanation?

Software-Agile
Go Premium

Agile Project Management Preparation Package (2024)

  • 606 Superior-grade Agile Project Management practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • Bonus: If you upgrade now you get upgraded access to all courses
  • Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!
More Burn-down Chart questions
17 questions (total)