Activity Sequencing

5 minutes 5 Questions

Activity Sequencing involves identifying and organizing the dependencies between different tasks in a project. Understanding how these tasks relate is crucial for defining the project order and structure. In CPM, compiling these relationships in a logical sequence determines the project's overall flow and lays the foundation for devising the project schedule. This aspect helps project managers anticipate potential bottlenecks and plan resources and timelines strategically.

Understanding Activity Sequencing in the Critical Path Method (CPM)

Why it is important:
Activity sequencing is a crucial part of any project management approach, and particularly so in the Critical Path Method (CPM). It enables project managers to identify the order of tasks that need to be performed for successful completion of the project. By understanding activity sequencing, one can optimize the project schedule and efficiently allocate resources, thereby achieving completion within the given time and budget constraints.
What is Activity Sequencing in CPM?
In the Critical Path Method, activity sequencing refers to the process of identifying and documenting the relationships between project activities. It includes identifying dependencies between tasks, and determining which tasks can be run in parallel and which must be run sequentially.
How it works:
Activity sequencing starts with a list of activities from the project work breakdown structure. These activities are then analyzed to find their dependencies, and are documented in an Activity Sequence Diagram. The diagram helps to visualize the order of operations and to identify the critical path - the sequence of activities that defines the shortest possible duration of the project.
How to answer questions regarding Activity Sequencing in an exam:
Understanding the terminology and process of activity sequencing is key to answering related exam questions. Be sure to fully comprehend the concept of dependencies and the different types of dependencies such as finish-to-start, start-to-start, finish-to-finish, and start-to-finish. Be ready to identify or formulate an Activity Sequence Diagram from provided data.
Exam Tips: Answering Questions on Activity Sequencing:
Always read and understand the question before starting your answer. If it asks for sequencing, make sure you mark the appropriate task dependencies and sequence in your answer. If a diagram is involved, label it clearly to show task sequences and dependencies. Always explain your reasoning when formulating the critical path and don't forget to use the correct terminology.

Test mode:
CAPM - Critical Path Method Example Questions

Test your knowledge of Amazon Simple Storage Service (S3)

Question 1

You are managing a civil engineering project. The preliminary design phase cannot start until the project requirements have been collected. The detailed design phase can only start when the preliminary design phase is finished. The construction phase cannot start until the detailed design is completed. What is the best way to sequence these activities?

Question 2

A pharmaceutical company is developing a new drug. The preclinical trials cannot start until the drug formulation is complete. Clinical trials can begin when preclinical trials are 80% complete. Manufacturing setup can start once clinical trials reach 50% completion. Regulatory submission can only occur after all clinical trials and 75% of manufacturing setup are finished. Marketing preparations can begin when regulatory submission starts. How would you best sequence these activities?

Question 3

As a project manager for a publishing house, you are coordinating the publication of a book. The content creation cannot start until the topic is selected. The editing process can start after half the content is written. The book printing cannot start until editing is finished. How should you sequence these activities?

Go Premium

Certified Associate in Project Management Preparation Package (2025)

  • Earn 15 PDUs needed for your CAPM certification
  • 4454 Superior-grade Certified Associate in Project Management practice questions.
  • Accelerated Mastery: Deep dive into critical topics to fast-track your mastery.
  • Unlock Effortless CAPM preparation: 5 full exams.
  • 100% Satisfaction Guaranteed: Full refund with no questions if unsatisfied.
  • Bonus: If you upgrade now you get upgraded access to all courses
  • Risk-Free Decision: Start with a 7-day free trial - get premium features at no cost!
More Activity Sequencing questions
34 questions (total)