Activity Sequencing

5 minutes 5 Questions

Activity Sequencing involves identifying and organizing the dependencies between different tasks in a project. Understanding how these tasks relate is crucial for defining the project order and structure. In CPM, compiling these relationships in a logical sequence determines the project's overall f…

Test mode:
CAPM - Activity Sequencing Example Questions

Test your knowledge of Activity Sequencing

Question 1

You are managing a civil engineering project. The preliminary design phase cannot start until the project requirements have been collected. The detailed design phase can only start when the preliminary design phase is finished. The construction phase cannot start until the detailed design is completed. What is the best way to sequence these activities?

Question 2

A pharmaceutical company is developing a new drug. The preclinical trials cannot start until the drug formulation is complete. Clinical trials can begin when preclinical trials are 80% complete. Manufacturing setup can start once clinical trials reach 50% completion. Regulatory submission can only occur after all clinical trials and 75% of manufacturing setup are finished. Marketing preparations can begin when regulatory submission starts. How would you best sequence these activities?

Question 3

As a project manager for a publishing house, you are coordinating the publication of a book. The content creation cannot start until the topic is selected. The editing process can start after half the content is written. The book printing cannot start until editing is finished. How should you sequence these activities?