Backward Pass

5 minutes 5 Questions

In contrast to the forward pass, the backward pass is a project network diagram technique used to determine the late start and late finish dates of unfinished activities. It works by moving backward through the network diagram. This method helps in pinpointing the tasks that could be delayed, witho…

Test mode:
CAPM - Backward Pass Example Questions

Test your knowledge of Backward Pass

Question 1

In a project with activities A-B-C-D-E, each taking 3 days, the project must finish in 18 days. If activity C finishes on day 9, what is the Late Start (LS) for activity E?

Question 2

In a project, task P (4 days), Q (3 days), R (2 days), and S (2 days) should be completed sequentially. If Q completes on the 7th day, when will S be completed?

Question 3

In a product development project, tasks are scheduled in sequence A-B-C-D. Task A has a duration of 4 days, B has 5 days, C has 3 days and D takes 2 days. The project must be completed in 14 days. If task B is completed on the 6th day, what would be the Late Start (LS) of task D?